Start-up
Bosch Rexroth AG, MIT: LU 2, 3 842 358 814/2018-12
• Make sure that all electrical connections are either used or covered. Make sure that
all screwed connections and plug-in connections are properly seated. All relevant
protective covers must be fi tted.
• Only inspect and adjust continuous conveyors that are in motion or operation when
the safety guards are in place.
• Adhere to DIN EN ISO 13857 when removing or replacing guards and/or bypassing
safety equipment.
• Test runs with open paneling should only be performed by a person with
appropriate knowledge and experience using tip switches, and if there is no
possibility of interference from other switching devices.
• Only start up the product if all safety equipment has been installed in the system
and is functional.
• Only start up a product that has been completely installed.
9.1.1

Short description commissioning

1.
Mount the drive to the oil container (see page 31)
2.
Set delivery volume (see page 17 and 20)
3.
Mount the drive with the oil container to the support bracket (see page 32)
4.
Connect connection cable (see page 32)
• After connecting the power cable and with supply voltage present, the LED
indicators fl ash green (GN) in 5s intervals.
• A fl ashing arrow icon
• The lubricating unit is ready for operation with the parameters previously set.

9.2 Re-commissioning after a standstill period

Follow the steps outlined for initial commissioning.
appears in the display.