For lifting the machine a fork lift truck with length of the forks at least 1200 mm is
needed.
- Provide a fork lift truck A with the necessary load-lifting capacity corresponding to the weight of
the machine
- The forks B approach the machine as it is shown on fig.3
If it is possible to use a crane or similar equipment proceed in the following way:
- Prepare 2 ropes or straps C with the necessary load-lifting capacity and length
- The ropes are hanged on the hook D of the crane, which must have load-carrying capacity
corresponding to the weight of the machine.
- The ropes are lifted with the crane and are hanged under the table of the machine
- Make sure that the working table is locked with the handle E.
The lifting and transportation of the machine must only be
carried out by qualified staff and must be carried out with
appropriate equipment.
Note that lifting equipment used (crane, forklift, sling, etc.) must be in perfect condition.
To maneuver the machine in the packaging can also a pallet jack or a forklift be used.
13.2.3 Preperation of the surface
Uncoated metal machine parts have been insulated with a greasy layer to inhibit corrosion.
This layer has to be removed. You can use standard solvents that do not damage the machine
surface.
Do not use solvents based on nitrite, aggressive solvents like break
cleaners or scrubbing agents!
These damage the machine surface.
HOLZMANN MASCHINEN Austria
All manuals and user guides at all-guides.com
www.holzmann-maschinen.at
OSZILLIERENDE KANTENSCHLEIFMASCHINE / OSCILLATING EDGE BELT SANDER
W A R N I N G
N O T I C E
APAREZCA AQUÍ.
Seite 34
KOS 3000C