CoolAir SP950I
6.7
Connecting condenser unit to evaporator unit
I
NOTE
The procedure for making the mechanical and electrical connection of the
evaporator unit to the condenser unit is available in the condenser unit's
installation manual.
➤ Route the long connection cable for the 24 V connection, in a curve out
through the opening in the floor of the condenser unit.
➤ Mount the remaining fastening holder (fig. 0, page 7).
➤ Fasten the 24 V connection cable using the size 10 clamp, the M6 screw, M6
washers and the M6 lock nut to the additional fastening holder (fig. a,
page 8).
A
NOTICE!
The clamp is used as a strain relief for the 24 V connection cable. The 24 V
connection cable must not slip through the clamp.
Secure the 24 V connection cable against chafing.
6.8
Installing the electrical supply lines
!
WARNING!
• The electrical power supply may only be performed by qualified personnel
with specialist knowledge.
• Make sure there is no voltage present on electrically operated components
before carrying out work on them!
A
NOTICE!
• Fit a fuse of 25 A to the connection to the vehicle's power supply.
• The battery must be able to supply the required current and voltage
(chapter "Technical data" on page 29).
I
NOTE
The unit is equipped as standard with a 4 m long cable with a cross-section of
2
8 mm
. If longer cable lengths are required, then the cable cross-section must
be increased by an authorised specialist workshop:
In this case, extend the cable using a 16 mm² cable. Make a professional
connection.
The 16 mm² cable must not be longer than 8 m.
EN
Installation
23