8 Checklist
We recommend that you print out and work through the checklist for commissioning and when
replacing the measuring system of a previously accepted system and store it as part of the overall
system documentation.
Documentation reason
Sub-item
Present user manual has
been read and understood
Check that the measuring
system can be used for the
present automation task on
the basis of the specified
safety requirements
Fulfillment of the installation
requirements defined in the
user manual
Requirement for the power
supply
Correct installation
System test after
commissioning and change of
the counting direction
Device replacement
Printed in the Federal Republic of Germany
10/11/2017
To note
–
●
Intended use
●
Compliance with all technical
data
●
Safe mechanical fixing of the
measuring system and safe
positive connection of the
driving shaft with the
measuring system
●
The power supply used must
meet the requirements of
SELV/PELV
(IEC 60364-4-41:2005)
●
Observance of the EMC-,
cable- and shielding-
requirements
●
During commissioning and
after each change of the
counting direction all affected
safety functions must be
checked
●
It must be ensured that the
new device corresponds to
the replaced device
●
All affected safety functions
must be checked
TR - ECE - BA - DGB - 0070 - 16
Date
Edited
Can be found under
Document no.:
TR-ECE-BA-DGB-0070
●
Chapter
Intended use, Page 69
●
Chapter
Technical Data, Page 102
●
Chapter
Assembly, Page 78
●
Chapter
Supply voltage, X1,
Page 88
●
Chapter
Installation / Preparation
for Commissioning,
Page 84
●
Chapter
Safety functions of the
fail-safe processing unit,
page 71
●
Chapter
Counting direction,
Page 92
●
Chapter
Counting direction,
Page 92
●
Chapter Replacing the
Measuring System,
Page 100
TR-Electronic GmbH 2009, All Rights Reserved
Checked
yes
Page 101 of 108