Commissioning
7
Before switching on
Note!
Do not change the switch-on sequence.
l
In the event of an error during commissioning please see the chapter "Fault
l
detection and elimination".
Check the following to avoid damage to persons or material...
...before the mains voltage is connected:
Completeness, short circuit and earth fault
l
"Emergency-off" function of system
l
Motor connection (star/delta) must be adapted to output voltage of controller.
l
If you do not use a function module ensure that the FIF cover is mounted properly (as
l
delivered).
If the internal voltage supply is connected, for instance, to X3/20 of the standard-I/O, terminals
l
X3/7 and X3/39 must be bridged.
... the most improtant drive parameter settings before the controller is enabled:
Are the parameters needed for your application set correctly?
l
– e. g. configuration of analog and digital inputs and outputs
34