8.4.2
Installation for measurement via 2 traverses
Requirements
• The installation distance is known → 9
• Strapping bands are pre-assembled
Material
The following material is required for mounting:
• Two strapping bands incl. mounting bolts and centering plates where necessary (already
pre-assembled → 19, → 21)
• A mounting rail to position the strapping bands:
• Short rail up to DN 200 (8")
• Long rail up to DN 600 (24")
• No rail > DN 600 (24"), as distance measured by sensor distance between the mounting
bolts
• Two mounting rail holders
• Two sensor holders
• Coupling medium (coupling pad or coupling gel) for an acoustic connection between the
sensor and pipe
• Two sensors incl. connecting cables
• Open-ended wrench (13 mm)
• Screwdriver
Procedure:
1.
Position the strapping bands using the mounting rail [only DN50 to 600 (2 to 24"), for
larger nominal diameters, measure the distance between the center of the strap bolts
directly]: Fit the mounting rail with the bore identified by the letter (from the Result
sensor distance / measuring aid parameter) over the mounting bolt of strapping band
1 that is fixed in place. Position the adjustable strapping band 2 and fit the mounting
rail with the bore identified by the numerical value over the mounting bolt.
17
Determining the distance according to the mounting rail (e.g. G22)
2.
Tighten strapping band 2 so that it cannot slip.
3.
Remove the mounting rail from the mounting bolt.
Endress+Hauser
G
22
EA01368D