Chapter 6
6
Commissioning and operation
WARNING
WARNING
90
Commissioning and
operation
Prior to initial commissioning, the machine or system
safety functions must be fully checked by specialist
personnel and also documented.
After every change and after maintenance and repair
work, the entire protective device must be checked
for effectiveness by specialist personnel.
6.1
Tests before the initial
commissioning
• Check observance of the conditions as per
chapter 4.
• Perform electrical function test on the sensor
together with a safety controller or a safe PLC.
6.1.1
Checking start function
The check must be performed separately for each pro-
tective device.
⋅ Deactivate the machine or the system.
⋅ Open the protective device.
Start the machine or system; if the safety function of
the protective device is correct, the machine or system
must not start.
If, nevertheless, the machine or system starts, again
check compliance with mounting conditions, the
correctness of all electrical connections and correct
the function of the safety system.
© SICK AG • Germany • All rights reserved
Operating Instructions
IN4000 Standard
8010934/ZWG9/2018-07-26
Subject to change without notice