5.4 Mains connection
1. Mains connection:
Mains connection is carried out using the
pre-assembled connecting cable with earthed plug.
2. Fresh water station must be earthed
PWM connection Power supply 230 V
Illustr. 5.2 Pump connections
5.5 Cable layout
230V AC
Power supply
earthed plug
brown = L1
blue = N
green/yellow = PE
green/yellow = PE
blue = N (230V AC)
brown = L1 (230V AC)
1
Flow switch
brown = br
(flow switch)
blue = bl
(flow switch)
Signal cable
flow switch
blue = bl (right hand side slot)
brown = br (left hand side slot)
)
Illustr. 5.3: Cabling
1 Electronic box
2 Flow switch
3 Pump primary circuit
Power supply pump
brown = L
blue = N
green/yellow = PE
Wilo Yonos Para
PWM2
brown = L (pump)
blue = N (pump)
green/yellow = PE
blue = bl (PWM)
brown = br (PWM)
Signal cable pump
blue = bl
brown = br
6 Operation
6.1 Initial operation
NOTICE
Before initial operation, tightness has to be checked
by submitting the system to a pressure test.
Damage to property caused by pressure
impacts
Sudden pressure impacts when opening the ball
valve may lead to damage to property
For this reason:
– Always open ball valves slowly
– Open ball valve of the cold water supply first
(flow direction)
Moreover, the system has to be flushed thoroughly
with due consideration of the permissible operating
pressures.
When the potable water circuit is closed, the
permissible operating pressure can be exceeded
All ball valves must be in the open position during
operation
WARNING
Damage to property through operating error
Operating errors and an incomplete installation
may cause malfunction and damage to property.
WARNING
The pipework has to be bled and flushed
thoroughly in order to guarantee a perfect
operation of the system.
Corresponding components (deaerator...) are to be
installed on site.
DANGER
Risk of scalding
Water pipes and the water drawn from the tap can
become very hot (> 60 °C).
For this reason:
– If necessary, preventive measure against scalding
are to be taken on site.
6.2 Flushing, filling
DANGER
Risk of injury
Improper use may lead to extensive injuries and
damage to property.
For this reason:
– Carry out leakage test before filling/flushing
– Have any work at the installation only carried
out by a qualified tradesmen.
– Wear safety goggles.
13