8.3. MAINTENANCE WORK
8.3.1. CLEANING
NOTE!
All cleaning agents must be compatible with the materials of the installed component.
8.3.2. REQUIREMENTS FOR MAINTENANCE
CHECK BEFORE MAINTENANCE START, IF:
Gas supply is disconnected and safe
Manifold is depressurized
Pressure regulator is depressurized
Valves are closed
No process gas inside component.
System is purged and fi lled with inert gas.
8.3.3. NECESSARY MAINTENANCE
Check accuracy of pressure gauges
Manifold, pressure regulator, valve and gauges: check condition, function and labeling
Check labelling
Check for corrosion
Check function
Pressure test with 1-times working pressure for 12 hours
Worn and defective components must be changed immediately from authorized qualifi ed company
Valve is designed according to ISO 10297, including type test with cycle test from up to 2000 cycles.
Change inner parts after 2000 cycles, change must be done from authorized qualifi ed company
If there are any leakages or too much corrosion at the manifold/ pressure regulator or valve, component
must be replaced with all connections by an authorized company
After the changing of components or tubes, pressure and leakage test must be done again and be proto-
colled
8.4. MEASURES FOLLOWING MAINTENANCE
THE FOLLOWING STEPS MUST BE PERFORMED WHEN THE MAINTENANCE WORKS HAVE BEEN
COMPLETED AND BEFORE SWITCHING ON THE SYSTEM:
1. Make sure that all tools, materials and other equipment have been removed from work area.
2. Clean the work area and remove any spilled substances, e.g. liquids, processing material or similar.
3. Make sure that safety relevant components are working perfect.
9. TROUBLESHOOTING
The following section describes possible causes of malfunction and how to eliminate them. If malfunctions
occur with increasing regularity, shorten the maintenance intervals to refl ect the actual load. If malfunctions
occur that cannot be eliminated with the following help, please contact the manufacturer.
9.1. SAFETY NOTES FOR TROUBLESHOOTING
In any case of malfunction, the shut-off valves oft he connected gas cylinder, gas container or bundle must
be closed. Never operate devices with malfunctions under pressure.
WHAT TO DO IN CASE OF MALFUNCTION:
1. Interrupt and ensure gas supply.
2. Depressurize pressure regulators and close valves.
3. Only trained technical staff may eliminate malfunctions.
4. Restore component to its original state.
23/380