Installation / Preparation for commissioning
5.2.2 Bus termination
If the measuring system is the last slave
in the PROFIBUS segment, the bus is to
be terminated with the termination
switch
subsequent PROFIBUS is decoupled.
5.2.3 Bus address
Valid PROFIBUS addresses: 3 - 99
0
10
: Setting the 1st position
1
10
: Setting the 10th position
The device does not start up with an
invalid station address.
5.2.4 Shield cover
The shield cover is connected with a special EMC cable gland, whereby the cable
shielding is fitted on the inside.
Prepare the PROFIBUS cable (e.g. 2-wire)
TR-Electronic GmbH 2004, All Rights Reserved
Page 72 of 115
=
ON.
In
this
state,
The dimension "X" depends on the type and size of the cable gland.
TR - ECE - BA - DGB - 00036 - 10
the
1
10
approx. 80 mm
X mm
ON
OFF
0
10
5mm
Printed in the Federal Republic of Germany