Safety Program Creation - Configuration Example
All necessary blocks are now displayed in the project window:
4.6 Loading the safety program
When the safety program has been generated, it can be loaded into the F-CPU. It is
advisable to transfer the complete safety program to the F-CPU in STOP operating
status. This guarantees that a consistent safety program is loaded. The program is
loaded with the menu Options --> Edit safety program --> Download switch.
4.7 Testing the safety program
After generating the safety program, a complete functional test must be carried out
according to the automation task.
After modifications to an already completely function-tested safety program, it is
sufficient to test the modifications.