ASSEMBLY
Mounting the pressure line
TWIN pumps
see Fig. A
1. Screw the connection elbow (7) into the pump
outlet.
2. Screw the combination nipple (4) onto the
connection elbow.
3. Fix a hose to the combination nipple.
SUB pumps
see Fig. C
1. Screw the combination nipple (4) onto the
connection elbow.
2. Fix a hose to the combination nipple.
The combination nipple can be trimmed
ADVICE
to suit the selected hose connection. Use
the largest possible hose diameter.
Setting the adjustable foot
see Fig. E
TWIN pumps
1. Turn the adjustable foot (6) to the right.
The adjustable foot disengages.
2. Set the adjustable foot to position "O" or "U".
3. Turn the adjustable foot (6) to the left.
The adjustable foot locks back in posi-
tion.
SUB pumps
1. Turn the adjustable foot 90° to the left to move
the adjustable foot to the top position.
2. Turn the adjustable foot 90° to the right to
move the adjustable foot to the bottom posi-
tion.
The combination nipple can be trimmed
ADVICE
to suit the selected hose connection. Use
the largest possible hose diameter.
STARTUP
Safety
CAUTION!
Exclude, by suitable means, that, in the
event of a fault in the immersion pump,
consequential damage is caused by floo-
ding.
16
Make sure that the immersion pump is stan-
ding securely or operate the immersion pump
suspended from a rope.
Make sure there is adequate clearance under
the pump.
Never allow the immersion pump to run
against a closed off pressure line.
When using in shafts, make sure the size is
adequate.
Always cover the shaft with a secure foot-
plate.
Switching the pump on
see Fig. A - C
CAUTION!
The immersion pump must not draw in
any solid bodies. Sand and other abra-
sive materials in the conveying medium
will destroy the immersion pump.
1. Unwind the connection cable (1) completely.
2. Make sure that the electrical plug connection
is mounted in the area safe from flooding.
Models with float switch
3. Change the terminal position and adjust the
switching points of the float switch(10) indivi-
dually.
4. Attach the cable on the float switch to the
pump housing(4)securely.
Recommended cable length on the float
switch approx. 100 mm
Models with level switch
5. Slide the level switch (8) to the relevant height
and thus set the switching points.
Use a suitable plate to ensure se-
ADVICE
cure mounting of the immersion
pump on muddy, sandy or stony
ground.
6. Immerse the immersion pump in the convey-
ing medium slowly. Hold the immersion pump
at a slight angle to allow any air to escape.
7. Insert the mains plug into the plug socket.
The immersion pump switches on auto-
matically using the float switch when a
specific water level has been reached,
and switches off again if the water drops
below the switch-off height.
Switching the pump off
1
Remove the mains plug from the plug socket.
SUB 10000-13000 DS / TWIN 11000-14000