Herunterladen Inhalt Inhalt Diese Seite drucken

Commissioning - EKOM DK50 2V/M Benutzerhandbuch

Vorschau ausblenden Andere Handbücher für DK50 2V/M:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

INSTALLATION
Connect the cabinet pressure gauge to the compressor per Chapter 11.2.
Connect the display in the front door of the cabinet (Fig. 15), and secure the cord to the
display in the clamps (Fig. 16).
Fig. 15: Connecting the display connector
Fig. 16: Position of the clamps in the cabinet

14. COMMISSIONING

Check if all fixing elements used during transport have been removed.
Check correct connection of compressed air (see chapter 11).
Check correct connection to the mains (see chapter 12)
Check position of the circuit breaker switch, it must be in position „I". If it is in position „0",
turn the switch (2) to position „I" (Fig. 17)
On compressor in the cabinet, switch the switch (5) on the front side of the cabinet to position
„I", the green light indicates the device status in operation. (Fig. 17).
12/2022