INSTALLATION
Connect the cabinet pressure gauge to the compressor per Chapter 12.2.
Connect the display in the front door of the cabinet (Fig. 15), and secure the cord to the
display in the clamps (Fig. 16).
Fig. 15: Connecting the display connector
Fig. 16: Position of the clamps in the cabinet

15. COMMISSIONING

Check if all fixing elements used during transport have been removed.
Check correct connection of compressed air (see chapter 12).
Check correct connection to the mains (see chapter 13)
Check position of the circuit breaker switch, it must be in position „I". If it is in position „0",
turn the switch (2) to position „I" (Fig. 17)
On compressor in the cabinet, switch the switch (5) on the front side of the cabinet to position
„I", the green light indicates the device status in operation. (Fig. 17).
Check connection of the cabinet manometer hose to the pneumatic block of the compressor.