en
28 | TCE 4460 | Initial commissioning
Pos.
Name
17
Movable lanes
18
Locking jaws
19
2 positions column lever
20
Inflation gauge
21
Inflation pipe
22
Deflation button
23
Bead lifting lever
24
Lubricator holder bulb
4.
Initial commissioning
4.1
Unpacking
1. Remove the tape and the fixing clamps from the
pallet and the packaging cardboard.
i
After unpacking check the integrity of TCE 4460 and
check that no components are visibly damaged. In
case of doubt do not proceed to start-up and con-
tact a qualified technician and/or your vendor.
2. Take out of the transport crate the standard accesso-
ries and the packaging materials.
i
Dispose correctly of packaging material, hand it over
to the designated collection points.
4.2
Assembly
4.2.1
Cover removal
1. Unscrew the 4 screws of the side cover and remove
the cover itself.
|
1 695 105 428
2010-02-16
Function
Positioning of the locking jaws.
Internal or external locking of the rim.
Operation of the 2 positions column (lifting and lowering).
Tire inflation check.
The manometer is compliant to CEE 87/217 directive.
Tire inflation with air chamber.
Tire defl ation.
Lifting of the tire edge in demounting and mounting phases.
Mounting paste containing support.
4.2.2
Lifting of the tilting column
1. Unscrew the fulcrum-pin screw of the column with
the hex key 6 and remove the pin.
2. Get a 1 Mt lifting sling, DR 50 model (safety factor
6:1); wrap the sling around the tilting column and lift
the column with a hoist.
3. Lean the column on the casing.
Robert Bosch GmbH