Installation
•
Observe the cable gland approval and installation information. Observe the instruction
manual 42/10-57 XU for the ABB supplied cable glands.
•
Check the line used with regards to suitability (type, actual line diameter, etc.).
•
Tighten the cable glands until the line is firmly enclosed by the sealing ring.
•
Protect the line from mechanical load (tension, torsion, etc.) using additional means.
•
Close unneeded openings with ignition-proof approved sealing elements.
Caution – Damage to parts!
Do not tighten cover with wrench (hexagonal wrenches and slots are opening aids solely). Do
not damage the threads!
•
Tighten the cover by hand until the cover seal is pressed together.
•
Secure the cover by screwing in the lock screw (check the cover threads first for damage).
3.5.4.1
Disassembly
Warning – general risks!
The cover may only be opened in a zero potential state.
Depending on the electrical components installed and the operating situation (fault etc.), a
sufficiently long waiting period for discharge and cooling must be complied with.
Observe the warning sign on the housing.
3.5.5
Intrinsic safety and hermetic sealing: ATEX II 1 G Ex ia IIC T6 and ATEX II 1/2 G Ex d IIC T6
See points 3.5.1 and 3.5.4
3.5.6
ATEX Ex nA - Zone 2 and 22
There are no additional specifics that must be observed for the mechanical installation.
10 - EN
SensyTemp TSP
CI/TSP-X1