Commissioning

Commissioning steps

Commissioning steps
Step
Procedure
1.
Switch on the mains
voltage.
2.
Control digital inputs.
3.
Provide a setpoint
4.
Release the controller via
the terminal.
5.
The drive should be running now.
44
Description
The basic device will be ready for operation after approx.
1 second.
The controller inhibit is active.
Drive response:
The green LED is blinking.
dc
Keypad:
(if attached)
Lenze setting:
l
CW rotation:
– E1, E2, E3, E4: LOW
l
CCW rotation:
– E1, E2, E3: LOW
– E4: HIGH
Individual setting:
l
Adapt digital inputs under C0007 or C0410.
l
The digital inputs must be controlled so that the drive
can start via terminal after controller enable.
Lenze setting:
Setpoint: 0 ... +10 V
Individual setting:
l
Depending on the position of the DIP switch at the
function module
– apply master current to X3/8 or
– Apply master voltage at X3/8.
l
Check C0034.
Lenze setting:
X3/28 = HIGH (+12 ... +30 V)
Drive response:
l
The green LED is on.
c
l
Keypad:
goes off.
l
EDK82ZAFSC−010 DE/EN/FR 6.1

Quicklinks ausblenden:

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Standard-i/o pt

Inhaltsverzeichnis