4
Operation
4.1 Display
4.2 Commissioning
NOTICE
Property damage as a result of exceeding technical specifications
• Comply with the technical specifications during normal operation.
• The pipeline pressure before the meter must not fall below 0.3 bar.
Execution:
1. Check with respect to firm screw connections on the pipeline and measuring in-
sert.
2. Slowly fill the pipeline with the medium.
3. Check with respect to response behaviour of the display.
The meter is ready for operation.
RUBIN HYZ ST, RUBIN HYZ RS
Whole cubic metres m
1
2
Cubic metre fractions
3
Cubic metre fractions
4
Cubic metre fractions
3
1
10
3
m
1
100
3
m
1
1000
3
m
43