Herunterladen Inhalt Inhalt Diese Seite drucken

Installing The Distribution Box Cover; Installing The Front Panel - Bosch BPT-S Hybrid Installationsanleitung

Inhaltsverzeichnis

Werbung

Verfügbare Sprachen

Verfügbare Sprachen

82 | Installation
Storage system | Installation manual
The string inverter is connected to the internal
distribution box.

6.10 Installing the distribution box cover

Procedure
1. Install the cover on the internal distribution box
2. Ensure that the earthing cable is connected from
the distribution box cover to the distribution box
housing. The earthing cable is prefitted in the
factory. (Earthing connections overview, p. 90)
The cover is installed.

6.11 Installing the front panel

Procedure
Info
In order to make it easier to install the front panel,
open the housing door
1. Place the front panel on the lower crossbar of the
housing
2. Install the switch plate of the front panel in the
bracket on the housing
3. Use the 8 mm spanner to secure the front panel
earthing cable to the point marked on the housing
with one M5 hex nut and washer
4. Use the 8 mm spanner to secure the front panel to
the inside of the housing at the bottom and half
way up on both sides, each with two M5 hex nuts
and washers
English
Bosch Power Tec GmbH

Werbung

Inhaltsverzeichnis

Fehlerbehebung

loading

Inhaltsverzeichnis