Installing the MPP solar charger
7.1

Installation location

When selecting an installation location, consider the following:
• The device should be installed close to the batteries to keep the battery connection cable as
short as possible.
• The mounting surface must be even and sufficiently hard.
• The device must be installed in a location that is protected from moisture and dust.
• There should be a space of 10 cm on all sides around the device.
7.2
Mounting the MPP solar charger
A
NOTICE! Damage hazard
Before drilling any holes, ensure that no electrical cables or other parts of the vehicle
can be damaged by drilling, sawing or filing.
➤ Mount the device with 4 screws vertically on a wall with the terminals pointing down.
7.3
Determine the cable cross-sections and fuses
Cable
connection
Solar panel
House battery
Starting battery
AES/RE
Fuse
House battery
Starting battery
7.4
Connecting the MPP solar charger
!
WARNING! Electrocution hazard
• Completely cover all solar panels with an opaque material during installation to pre-
vent electricity from being generated.
• Observe the recommended cable cross-sections, cable lengths and fuse (chapter
"Determine the cable cross-sections and fuses" on page 20).
20
Cable
MT MPP 170
length
(as needed)
2.5 – 4 mm²
< 2 m
2.5 – 4 mm²
(as needed)
(as needed)
MT MPP 170
MT MPP170, MT MPP260, MT MPP440
MT MPP 260
4 –6 mm²
4 –6 mm²
1.5 – 2.5 mm²
0.5 – 1.5 mm²
MT MPP 260
15 A
MT MPP 440
6 – 10 mm²
6 – 10 mm²
MT MPP 440
20 A
5 A