Refrigerant Piping - Toshiba RAV-SM1102AT-E Installationshandbuch

Ausseneinheit
Vorschau ausblenden Andere Handbücher für RAV-SM1102AT-E:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 32
3
SELECTION OF INSTALLATION
How to remove the front panel
1. Remove screws of the front panel.
2. Pull the front panel downward.
Removing the front panel, the electric parts appear at
the front side.
• The metal pipes are attachable to the piping holes.
If the size of the used power pipe does not match
with the hole, adjust the hole size to match with pipe
size.
• Be sure to fix the power cable and indoor/outdoor
connecting cable with bundling band sold on the
market so that they do not make contact with the
compressor and discharge pipe.
(Temperature of the compressor and discharge pipe
becomes high.)
4

REFRIGERANT PIPING

Pipe Forming/End Positioning
Flaring
1. Cut the pipe with a pipe cutter.
OK
90˚
2. Insert a flare nut into the pipe, and flare the pipe.
As the flaring sizes of R410A differ from those of
refrigerant R22, the flare tools newly manufactured
for R410A are recommended.
However, the conventional
tools can be used by adjusting
projection margin of the copper
pipe.
• Flaring size : A (Unit : mm)
Outer dia. of copper pipe
6.4
9.5
12.7
15.9
All manuals and user guides at all-guides.com
NO GOOD
Obliquity
Roughness
Warp
A
+0
A
- 0.4
R410A
R22
9.1
9.0
13.2
13.0
16.6
16.2
19.7
19.4
In order to avoid the force applied to on the connect-
ing section, be sure to fix the cables to the cord
clamps provided on the pipe valve fixing plate and the
electric parts box.
Cord clamp
• Projection margin in flaring :
B (Unit : mm)
Rigid (Clutch type)
Outer dia.
R410A tool used
of copper
R410A
pipe
6.4
0 to 0.5
(Same as left)
9.5
0 to 0.5
(Same as left)
12.7
0 to 0.5
(Same as left)
15.9
0 to 0.5
(Same as left)
Imperial (Wing nut type)
Outer dia. of copper pipe
6.4
9.5
12.7
15.9
* In case of flaring for R410A with the conventional
flare tool, pull it out approx. 0.5 mm more than that of
R22 to adjust to the specified flare size. The copper
pipe gauge is useful for adjusting projection margin
size.
7
Electric parts box
Service panel
Pipe valve
fixing plate
Wiring
hole
Conventional tool used
R22
R410A
R22
1.0 to 1.5
0.5 to 1.0
1.0 to 1.5
0.5 to 1.0
1.0 to 1.5
0.5 to 1.0
1.0 to 1.5
0.5 to 1.0
R410A
R22
1.5 to 2.0
1.0 to 1.5
1.5 to 2.0
1.0 to 1.5
2.0 to 2.5
1.5 to 2.0
2.0 to 2.5
1.5 to 2.0
B