Installation Procedures
3. Preparation before Installation
(1) Locate
right
Model
40VD005-016S-7S-QEE
40VD018-030S-7S-QEE 1161
40VD038-054S-7S-QEE 1561
( 2) If necessary, make a hole for installation and access in the ceiling.(used for installation in a ceiling)
• For the size of the inspection hole in the ceiling, please refer to the above drawing.
• Before installation, finish all the preparations for all piping connected to indoor units (refrigerant, water, drainage)and
wiring(connection line of the line control, connection line between indoor units and outdoor unit)so that they can be
connected with indoor units right after installation.
• For the inspection hole, the ceiling might be reinforced to maintain the evenness of the ceiling and avoid the
vibration of the ceiling. For details, please consult the construction contractor.
(3) Install the hanger bolts (M1O bolts)
In order to support the weight of the unit, use barb bolts for installing in a ceiling. For installation in a new
ceiling, use inlaid bolts, embedded bolts or other parts
provided on site. Before proceeding with the installation,
adjust the gap between the bolt and the ceiling.
(4) Installation of Indoor Units
•
Fix the indoor unit with the hanger bolt. If necessary,
the machine can be hung with a Hanger on the beam.
Adjusting the level
Adjust the level with a level meter or in the following ways:
• Make the adjustment as shown in the figure.
Size
A
C
(mm)
(mm)
(mm)
761
619
7OO
619
11OO
619
15OO
top
E
M1Onut
Main unit
7
768
C
notch grapping
plug
notch plug
concrete
hoisting stud M1O
hoisting stud
M1Oshim
M1O spring washer
347mm
Level meter