INE SpA Via Facca, 10 - 35013 Cittadella - PADOVA - ITALIA Tel. 049/9481111 - Fax 049/9400249 - ine@ine.it - www.ine.it
•
Duty cycle: balance between welding current timing
and base current timing (e.g., a 50% duty cycle
means that welding current timing equals the base
current timing, a 30% duty cycle means that the
welding current timing is lower than the base current
timing).
•
Start current: value of initial current or first level (in
Amperes or %).
•
Final current: value of end current or third level (in
Amperes or %).
•
Start time: duration of initial current or first level
(only for 2-level mode and advanced 2-stroke).
•
Final time: duration of end current or third level (only
for 2-level mode and advanced 2-stroke).
•
Current 2: second level current value (in Amperes or
%); only for 2-level mode.
•
Welding time (SPOT): duration of a welding cycle.
•
Tack: duration of initial pulse to start bonding the
pieces, starting from the outer edge without too
much deformation (available only in TIG DC).
•
Maximum current of remote control: allows to set
the maximum value of the current for the remote
control.
Page 29