3. Open the differential pressure valve (
4. Check and if required correct the zero point when the start of scale value is 0 mbar (4 mA).
5. Close the stabilizing valve
6. Open the other differential pressure valve (
5.3.3
Commissioning for liquids
Usual arrangement
①
Pressure transmitter
②
Equalizer valve
③
④
Differential pressure valves
,
⑤
Differential pressure lines
⑥
Shut-off valves
Transmitter below the differential pressure transducer
Condition
All valves are closed.
Procedure
WARNING
The transmitter should not be depressurized if toxic substances are being used.
To commission the transmitter with liquids, proceed as follows:
1. Open both the shut-off valves
2. Open the equalizer valve
SITRANS P500 with HART
A5E02344532-03, 04/2013
③
④
or
).
②
.
③
④
or
⑥
at the pressure tapping point.
②
.
).
Special arrangement
⑦
Drain valves
⑧
Gas collector vessels (optional)
⑨
Differential pressure transducer
⑩
Vent valves
Transmitter above the
differential pressure transducer
21