Installing the heater
S 3004 / S 3004 P
Fig. A (right-hand installation) / fig. B (left-hand installation)
The thermostat sensor (5) must always be fitted to the
front of the heater (room side). The thermostat sensor (5)
and capillary pipe (6) must not touch the heat exchanger or the
heater panelling or be kinked under any circumstances.
Left-side installation only
Remove thermostat sensor (5) carefully at the snap-in clips
and place on the opposite side (mirror-inverted) until it snaps
into position.
– Place heater in the floor cut-out.
– Secure device with 5 screws (3) 5.5 x 25 to the prepared
points in the corners and secure in the middle at the front.
Reinforce the floor structure at the screw-in points using
battens, for example.
– Remove control rod (7) from the support (60), insert through
the bush of the support from underneath and engage in the
safety pilot valve (8).
60
5
6
Fig. 5 / * S 3004 P only
S 3004 P – piezo ignitor preparation
– Push the earth spring (14) out of the transportation lock so
that it is touching the installation box (otherwise the ignitor
will not function).
– Secure electrode cable (16) at control rod side using cable
clip (17) of installation box. Route electrode cable via instal-
lation box and slide through recess in support.
– The piezo ignitor must be installed at the control rod side.
Bend up the right (R) or left (L) ground contact of the instal-
lation box.
R
Fig. 6
18
7
*
16
17
8
16
14
*
3
16
L
S 5004
Fig. A (right-hand installation) / fig. B (left-hand
installation)
The thermostat sensor (5) must always be fitted to the
front of the heater (room side). The thermostat sensor (5)
and capillary pipe (6) must not touch the heat exchanger or the
heater panelling or be kinked under any circumstances.
Left-side installation only
Remove thermostat sensor (5) carefully at the snap-in clips
and place on the opposite side (mirror-inverted) until it snaps
into position.
– Place heater in the floor cut-out.
– Clip thermostat sensor (5) with heat screen onto screws.
5
6
Fig. 7
– Secure device with 5 screws (3) 5.5 x 25 to the prepared
points in the corners and secure in the middle at the front.
Reinforce the floor structure at the screw-in points using
battens, for example.
– Remove control rod (7) from the support (60), insert through
the bush of the support from underneath and engage in the
safety pilot valve (8).
3
Fig. 8
7
60
8