Herunterladen Inhalt Inhalt Diese Seite drucken

Selection Of Location; Inspecting And Handling The Unit Errore. Il; Unpacking And Placing The Unit - Daikin EWWD120J-SS Bersetzung Der Originalanweisungen

Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 19
Ballvalve liquid pipe
Main isolator switch
Filter
(only for EWWD J, EWWH-J, EWWS-J)
Flowswitch
(only for EWWD J, EWWH-J, EWWS-J)

4. SELECTION OF LOCATION

The units are designed for indoor installation and should
be installed in a location that meets the following
requirements:
1.
The foundation is strong enough to support the
weight of the unit and the floor is flat to prevent
vibration and noise generation.
2.
The space around the unit is adequate for
servicing.
3.
There is no danger of fire due to leakage of
infiammable gas.
4.
Select the location of the unit in such a way that the
sound generated by to the unit does not disturb
anyone.
5.
Ensure that water cannot cause any damage to the
location in case it drips out the unit.
NOTE
Pull-down operation is restricted to one
hour maximum.
5. INSPECTING AND HANDLING THE
UNIT
At delivery, the unit should be checked and any damage
should be reported immediately to the carrier claims
agent.
When handling the unit, take into account the following:
1.
List the unit preferably with a crane and belts in
accordance with the instructions on the unit.
The length of the ropes (1) to be used for lifting are
4 m minimum each.
2.
The unit is shipped with wooden beams (2) under it,
these have to be removed before installation.
NOTE
Try to reduce the drilling in the unit to a
minimum. It drilling is impreventable,
remove the iron filling thoroughly in order
to prevent surface rust.
6. UNPACKING AND PLACING THE
UNIT
1.
Remove the wooden beams from the unit.
2.
Install vibration mountings in case of an
installation where noise and vibration might
an impediment.
3.
Set the unit on a solid and level foundation.
The unit should be installed on a solid base. It
is recommended to fix the unit on a concrete
base with anchor bolts.
1.
Anchor bolt
2.
Washer
3.
Rubber plate
4.
Row cork or rubber sheet
5.
Ground
6.
Concrete floor
7.
Ditch
Fix anchor bolts into the concrete foundation.
When finally fixing the unit by means of
these anchor bolts, make sure
washers for channel DIN434, and both field
supplied rubber plates and field supplied raw
cork or rubber sheets for better vibration
protection, are installed as indicated.
The concrete foundation should
approximately be 100 mm higher than the
floor level for ease of plumbing work and
better drain.
Model
EWWD120J~180J
EWLD 110J~165J
EWWH090J-130J
EWLH080J-130J
EWWS120J-180J
EWLS110J-170J
EWWD210J~280J
EWLD 195J~265J
EWWH150J-200J
EWLH140J-190J
EWWS200J-270J
Make sure that the foundation surface is even and flat
NOTE
The measurement tabulated is based on the fact
the base is made in the ground or on a concrete
floor. In case the base is made on a rigid floor, it is
possible to include thickness of concrete floor in
that of the base.
In case a base is made on concrete floor, make
sure to provide a ditch as shown. It is important to
extract drainage regardless of whether a base is
made in the ground or on the concrete floor (ditch-
sewerage).
D-EIMWC01008-16_01EU - 7/171
that the
Anchor bolt
A
Size
Qty
300
M20x200
4
350
M20x200
4

Werbung

Inhaltsverzeichnis
loading

Inhaltsverzeichnis